Ola Electric has set out a plan to lift its battery cell capacity to 20 GWh, the full amount of its allocation of up to 20 GWh under the government's advanced chemistry cell PLI scheme, from the 6 GWh now commissioned at its Krishnagiri gigafactory in Tamil Nadu. The roadmap was laid out on the company's Q2 FY27 earnings call on November 12, 2026, where chairman and managing director Bhavish Aggarwal said the money for this phase would come from outside investors taking equity in the cell subsidiary. Management told analysts the larger plant is not a matter of the next couple of quarters: getting the existing 6 GWh to run steadily comes before any further build-out.13

According to Aggarwal, the step up to 20 GWh will need far less spending than the first phase, and blended capital expenditure across the full plant should end up below Rs 400 crore per GWh. Autocar Professional explained the gap: the buildings and infrastructure were sized for 20 GWh from the outset, which cuts the civil and structural spending later phases need. An Ola spokesperson told Digit that the company also holds land at the site with room for more than 100 GWh. Ola is exploring sales of cells to other manufacturers and wants to use spare output in its Shakti storage products, though Trade Brains noted it has not disclosed any confirmed outside contracts or volumes.123

For now the cell unit is small. Trade Brains reported September-quarter revenue of Rs 3 crore for it and an adjusted operating EBITDA loss of Rs 38 crore. By management's reckoning, in-house cells cost about the same as bought-in ones once yield reaches roughly 70%, and become 10-15% cheaper on a cell gross-margin basis at an 85% yield. The company expects the unit's running and fixed costs to be covered, compared with buying cells, at consumption of about 2-3 GWh, a level it expects its own vehicles to reach in FY28. Ola put its NMC yield closer to 80% in November, Digit reported; Trade Brains put the current yield at 70-75%, and Autocar Professional at the mid-70s.123

CFO Deepak Rastogi said PLI incentives should begin in Q3 FY27, since Ola is running ahead of the scheme's milestones. Outside vehicles, the company intends to use its locally made cells in Mahashakti, a grid-scale battery it has planned; Autocar Professional said it is pitched at the Indian market, where new rules require 40% local value addition for such projects.1

Ola told Digit it wants more than 60% of its cell inputs to be local in the near term. Today only the electrolyte and some mechanical parts are. Most of the rest comes from abroad: electrode materials from China, Japan and South Korea, some specialised equipment, and separators from outside suppliers. Ola says it now has approved sources for its key materials in countries other than China, and it is testing an Indian-made LFP cathode.3

In its own testing, Ola said, the 4680 Bharat Cell retained 90% of its capacity after 1,000 charge-discharge cycles. Its 46100 LFP cell is certified by the Bureau of Indian Standards, and Ola aims to put it in vehicles by around March-April 2027. Drone makers are trialling the 46100 NMC version, while sodium-ion and solid-state work has not left the lab. "We have no firm volume-production dates for these programmes," the spokesperson said.3